On this page you’ll find answers to some of the most frequently asked questions about North Humber to High Marnham.
About the project
North Humber to High Marnham is a proposal for a new high voltage overhead electricity transmission line. The project would add much-needed capacity by upgrading the electricity transmission network between a new substation to the north of Hull and a new substation at High Marnham in Nottinghamshire. You can read more about the detail of our proposals on our website here.
With growing offshore wind and interconnectors, an anticipated tripling of wind generation connected across the Scottish networks by 2030 and the Government’s increased ambition to connect 50 GW of offshore wind by 2030, north-south power flows are set to increase. If all of the proposed new offshore wind that is planned to connect in the Creyke Beck area gets built, this would amount to just under 12 gigawatts (GW) of generation capacity by the early 2030s.
The existing network serving the Creyke Beck area can export just under 7 GW of electricity while remaining compliant with the Security and quality of supply standards to which the network is operated. The network as it is today would not have the capacity needed to export the significant forecast increase in contracted generation out of the area or to accommodate the north–south power flows that are expected on the network. We therefore need to increase the capability of the electricity transmission network between the north of England and the Midlands.
Before we build new infrastructure, we make sure we have done everything possible to get greater capability out of the existing network, including to accelerate the connection of clean energy projects. While there are several network upgrade projects planned, North Humber to High Marnham is an essential new reinforcement that forms part of The Great Grid Upgrade and is one of 17 network reinforcements identified as ‘essential’ and which need to be accelerated to meet 2030 targets.
Without these upgrades, the network won’t have the capacity that is needed to move electricity from where it is produced to where it is needed. Therefore, we need to upgrade it to maintain system compliance and prevent overloading circuits as they transport the energy that is generated. The Project would support the UK’s net zero targets by adding capacity to accommodate increasing power flows of energy. This is generated mostly from offshore wind in Scotland and North East England, which is expected to double within the next ten years, to areas of demand south to the Midlands and beyond. By reinforcing the network in the centre of the country, the project will facilitate the connection of more renewable and low carbon electricity, to allow clean green energy to be carried around the network.
We have held multiple consultations since 2023. During the remainder of 2025 and throughout 2026, we reviewed feedback, carried out further technical, environmental and ground investigation surveys, and continued engagement with landowners, local authorities and other stakeholders. This work helped us refine the project.
In 2026, we also asked local communities how a future Community Fund should be delivered, with feedback highlighting support for community facilities, health and wellbeing, environmental improvements and energy efficiency measures.
In October 2026, we submitted our Development Consent Order application to the Planning Inspectorate. The application, which includes our final proposals, environmental assessments and a Consultation Report explaining how feedback has been considered, was accepted for examination in November 2026.
The application is now in the pre-examination stage, during which time the Planning Inspectorate has appointed an independent Examining Authority and published details of how people can register as Interested Parties.
Our Development Consent Order application has been accepted for examination by the Planning Inspectorate and the project is now in the pre-examination stage. During this time, the Planning Inspectorate has appointed an independent Examining Authority and publish details of the period in which people can register as Interested Parties by submitting a Relevant Representation. Acceptance confirms that the application meets the required standards to proceed; it does not mean the project has been approved.
Some environmental and technical surveys may continue as the application progresses through the planning process, and we will continue engaging with landowners, local authorities and communities.
Yes. National Grid has reviewed all feedback received throughout our multiple consultation exercises, alongside technical, environmental and land surveys. This work has helped the project team refine the proposals and, in some locations, has resulted in changes to the draft order limits - the land that may be needed to build, operate and maintain the project.
Further detail on how feedback has been considered is set out in the Consultation Report submitted as part of the Development Consent Order application.
The project is now in the pre-examination stage. During this time, there is a set period when people can register with the Planning Inspectorate to become an Interested Party by submitting a Relevant Representation. A Relevant Representation is a short written summary of your views on the application. More information on how to make a Relevant Representation can be found here.
You can submit a Relevant Representation on the Planning Inspectorate's website here. Registering as an Interested Party allows you to make representations about the application and ensures you are kept informed about the progress of the examination and the final decision. The deadline for submitted a Relevant Representation is 11:59pm on Tuesday 5 January 2027.
For our application documents we have split the project into six geographic areas. These sections replace the 11 we used to describe the project at previous rounds of consultation. The table below shows the Route Sections within the application and the corresponding sections shown during our pre-application public consultations.
Route sections within the application for development consent | Corresponding route sections at statutory consultation
|
Route Section A Between the proposed Birkhill Wood Substation and the River Ouse
| Route Section 1 – between Creyke Beck and Skidby Route Section 2 – between Skidby and the A63 dual carriageway Route Section 3 – between A63 dual carriageway and the River Ouse crossing
|
Route Section B Between the River Ouse and Crowle
| Route Section 4 – the River Ouse crossing Route Section 5 – between the River Ouse crossing and Luddington Route Section 6 – between Luddington and the M180 motorway
|
Route Section C Between Crowle and North Moor (M180)
| Route Section 6 – between Luddington and the M180 motorway
|
Route Section D Between North Moor (M180) and the River Idle
| Route Section 7 – between the M180 motorway and Graizelound Route Section 8 – between Graizelound and the Chesterfield Canal
|
Route Section E Between the River Idle and Darlton
| Route Section 8 – between Graizelound and the Chesterfield Canal Route Section 9 – between the Chesterfield Canal and the A620 east of North Wheatley Route Section 10 – between the A620 east of North Wheatley and Fledborough
|
Route Section F Between Darlton and the proposed High Marnham Substation
| Route Section 10 – between the A620 east of North Wheatley and Fledborough Route Section 11 – between Fledborough and High Marnham
|
Yes. Surveys may continue as the project progresses through the next stages of the planning process. These surveys may include environmental, ecological, archaeology, engineering and ground investigation work. Some surveys can be carried out from public land or public rights of way, but where access to private land is required, National Grid or its appointed representatives will seek to agree access with the relevant landowner or occupier. Please see the Landowners and surveys page for more information.
About National Grid
National Grid sits at the heart of Britain’s energy system, connecting millions of people and businesses to the energy they use every day. We bring energy to life – in the heat, light and power we bring to our customers' homes and businesses; in the way that we support our communities and help them to grow; and in the way we show up in the world. It is our vision to be at the heart of a clean, fair and affordable energy future.
Within the National Grid Group there are distinctly separate legal entities, each with their individual responsibilities and roles. More information on National Grid can be found here.
National Grid Electricity Transmission owns, maintains and operates the high voltage electricity transmission network in England and Wales. This network operates primarily at 400 kilovolts (kV) and 275 kV.
National Grid Strategic Infrastructure is developing the proposals for North Humber to High Marnham. The proposals form part of The Great Grid Upgrade, which is the largest overhaul of the electricity grid in generations.
Contact the team
If you have any questions or comments about North Humber to High Marnham, please get in touch by emailing [email protected], by calling 0808 189 1346, or by writing to Freepost NH TO HM.
If you are a landowner and believe your property may be affected by our proposals, to speak to our Lands team you can email [email protected], call 0333 188 3511 or write to Unit 1, Staplehurst Farm, Weston on the Green, OX25 3QU.
What's energy resilience got to do with movie marathons?
Find out how – and why – we’re connecting more clean energy to power the things you love.