Vegetation management plans: Assington and Leavenheath

Between mid-September and the end of October 2026, we're carrying out vegetation management works at various locations along the route of the project. This post summarises the works planned in and around Assington and Leavenheath.

What's happening?

Between the middle of September and the end of October, we're carrying out vegetation trimming, pruning, coppicing and removal works at various locations. 

Some of the vegetation works will take place alongside public roads. We’ve therefore applied for a series of traffic management permits from Suffolk County Council, who are the local highways authority. This is so we can keep everyone safe whilst the works are carried out. Some of the permits for these works have already been approved, whilst others are still being reviewed by the Council.

To help people plan their journeys, this update includes an overview of all the works currently planned in and around Assington and Leavenheath. These dates are subject to change, particularly where we’re still waiting for a permit to be approved. 

Image
Types of traffic management explained

Why are you doing this?

We need to carry out vegetation management works for several reasons. For example, where the new overhead line passes over existing vegetation, we need to maintain a safe distance between the top of the vegetation and the overhead line. In areas where we are building a temporary new haul road, we need to manage or remove vegetation where it could cause visibility issues for construction vehicles entering or exiting the haul road. 

We’re carrying out these works now as this is one of two times in the year that Natural England has granted us a dormouse mitigation licence. It’s also outside of nesting bird season. You can find out more about why we need to carry out vegetation management on our website here.

Planned works

The map and table below shows the traffic management works associated with vegetation management between now and the end of October. This map and table is correct at the time of publication. 

For the latest updates, please see the 'What's happening now?' page of our website. You can also sign-up for updates via WhatsApp here.

Image
Map of location of traffic management measures
Road nameType of traffic managementWhat3words
 
Dates
 
TimingsNote
High Road, Honey TyeRoad closure with diversionmarkets.fend.tabs to defenders.tentacles.verve15 - 18 September8am – 5pmPermit approved
Bures Road, Dorking TyeRoad closure with diversionthickens.identity.boater to single.throw.intervene19 - 20 September9:30am - 2:30pmPermit approved
High Road, Honey TyeTemporary obstruction (15-min delay)markets.fend.tabs to defenders.tentacles.verve20 September only8am - 5pmPermit approved
Bures Road, Dorking TyeTemporary obstruction (15-min delay)thickens.identity.boater to single.throw.intervene21 - 22 September8am - 5pmPermit approved
B1068 Stoke RoadTwo-way traffic lightshaunts.vision.passwords24 September - 2 October8am - 5pmPermit approved
Dorking TyeRoad closure with diversionsparkles.amicably.wheat to supposes.hypocrite.logbook26 - 27 September9:30am - 2:30pmPermit approved
Dorking TyeTemporary obstruction (15-min delay)rifled.potential.label to variously.kitten.disengage29 September only8am - 5pmPermit approved
A134 Nayland RoadTwo-way traffic lightspampering.fines.standards21 - 25 October9:30am - 3pmPermit approved