What's happening now?

Our approved plans for the Bramford to Twinstead Reinforcement include:

  • building approximately 18 km of new 400 kV overhead line
  • building approximately 11 km of new 400 kV underground cable
  • removing around 27 km of existing 132 kV and 400kV overhead line between Burstall Bridge and Twinstead Tee
  • additional works to support construction, including temporary construction compounds, site offices, haul roads and new road junctions (bellmouths)
  • works to deliver a minimum of 10% biodiversity net gain, including planting and other environmental enhancements.

We are also building a new substation at Twinstead Green (between Butler's Wood and Walegrave Wood). The substation is where National Grid's high voltage transmission network connects into the low voltage network run by UK Power Networks, who is the distribution network operator in this area. We applied to build the GSP substation through a separate planning application to Braintree District Council, as this will reduce the overall amount of time it will take to build the project.

You can view the detailed plans included in our application for development consent by visiting the Planning Inspectorate's website here.

Current and upcoming works

Across the first half of this year, we've focused on building construction accesses and a temporary haul road so that we can reduce the need for construction traffic to use existing roads. We’ll continue to work on these over the next few months. To do this, we’ve had to carry out vegetation management (such as trimming, pruning, coppicing or removal) at various locations. The next phase of these works is planned from mid-September until the end of October. You can read more about why we need to carry out these works here.

In the autumn, we’ll take delivery of some of the cabling that will form part of the new transmission line. We will then begin underground cable works at various locations, and construction of the new overhead line will start to ramp up.

Traffic management 

When we carry out works near to or on the public highway, we often need to use traffic management (such as temporary traffic lights or road closures) to help keep you and our construction workforce safe. 

To make it easier to see the works planned for your area, we have split the route of the project into four sections. In each section, a table shows the current and upcoming works for the area. These dates are subject to change, and we update these tables regularly as new works are planned.

    Between now and the end of October, we need to carry out vegetation works at various locations in this area. These works are included in the table below, and also summarised here.

    Road nameType of traffic managementWhat3words
     
    Dates
     
    Timings
    Church HillTemporary Obstruction (15-min delay)
     
    elbowing.grudging.crisper to parsnip.shelf.botanists
     
    14 September to 16 September8am - 5pm
    A1071 Back Road
     
    Two-way traffic lightstowers.ratio.huddling to defends.tentacle.verve
     
    15 September to 18 September8am - 5pm
    B1070 Pipkin Hill
     
    Two-way traffic lightsshred.brisk.sharpness
     
    25 September to 29 September9:30am - 2:30pm on weekdays, 8am - 5pm on weekends
     
    Pond Hall RoadTwo-way traffic lightslooks.corner.pheasants to varieties.gossiped.meaning14 October to 16 October10am - 3pm
    Pond Hall RoadTwo-way traffic lightsmilder.goes.nylon to dignity.allowable.streetcar17 October only8am - 5pm
     
    Pond Hall RoadTemporary Obstruction (15-min delay)pixel.storeroom.wolf to boots.snapping.tenure 18 - 20 October10am - 3pm
    Pond Hall RoadTemporary Obstruction (15-min delay)skies.quest.tablets to deed.truffles.bends23 October only10am - 3pm
    Clay LaneRoad closure with diversionpunt.swatted.juicy to drummers.sunbeam.node26 October to 28 October8am - 5pm
    Clay LaneTemporary Obstruction (15-min delay)punt.swatted.juicy to drummers.sunbeam.node29 October to 31 October8am - 5pm

    Between now and the end of October, we need to carry out vegetation works at various locations in this area. These works are included in the table below, and also summarised here.

    Road nameType of traffic managementWhat3words
     
    Dates
     
    Timings
    White Street GreenRoad closure with diversionoven.buggy.ambushes18 August - 18 September24 hours a day, 7 days a week
    Millwood RoadRoad closure with diversionwages.winning.incurring to untruth.hedgehog.solids18 - 19 September8am – 5pm
    White Street GreenTemporary obstruction (15-min delay)oven.buggy.ambushes19 - 23 September8am - 5pm
    Popes Green LaneRoad closure with diversionincisions.grazes.chair to butchers.crystals.yard20 September only8am - 5pm
    Millwood RoadTemporary obstruction (15-min delay)wages.winning.incurring to untruth.hedgehog.solids21 September only8am - 5pm
    Popes Green LaneTemporary obstruction (15-min delay)incisions.grazes.chair to butchers.crystals.yard22 September only8am - 5pm
    B1070 Pipkin Hill
     
    Two-way traffic lightsshred.brisk.sharpness
     
    25 - 29 September9:30am - 2:30pm on weekdays, 8am - 5pm on weekends
    Holt RoadTemporary obstruction (15-min delay)events.succeed.resembles28 September - 1 October8am - 5pm
    Rands RoadRoad closure with diversionobvious.immunity.lads to alley.banks.mildest3 October only8am - 5pm
    Rands RoadTemporary obstruction (15-min delay)obvious.immunity.lads to alley.banks.mildest6 October only8am - 5pm
    Heath RoadRoad closure with diversionnanny.dream.hardly to loved.darts.image8 - 18 October7:30am - 6:00pm
    Rands RoadTemporary Obstruction (15-min delay)adopts.tumble.absorbing to wobbles.smokers.drop12 - 16 October8am - 5pm
    Heath RoadRoad closure with diversionevolving.shallower.sweated19 October - 15 November24 hours a day, 7 days a week

    Between now and the end of October, we need to carry out vegetation works at various locations in this area. These works are included in the table below, and also summarised here.

    From the end of September until mid-November, we're delivering construction materials to our main construction compound, near Leavenheath. No road closures are planned as part of this work, but the delivery vehicles will be larger than normal and could therefore cause some disruption to your journey. You can read more about how these deliveries will take place here. 

    Road nameType of traffic managementWhat3words
     
    Dates
     
    Timings
    B1508 St Edmunds HillRoad closure with diversionditching.transmit.investor14 - 25 September9:30am - 2:30pm
    High Road, Honey TyeRoad closure with diversionmarkets.fend.tabs to defenders.tentacles.verve15 - 18 September8am – 5pm
    Bures Road, Dorking TyeRoad closure with diversionthickens.identity.boater to single.throw.intervene19 - 20 September9:30am - 2:30pm
    High Road, Honey TyeTemporary obstruction (15-min delay)markets.fend.tabs to defenders.tentacles.verve20 September only8am - 5pm
    Bures Road, Dorking TyeTemporary obstruction (15-min delay)thickens.identity.boater to single.throw.intervene21 - 22 September8am - 5pm
    B1068 Stoke RoadTwo-way traffic lightshaunts.vision.passwords24 September - 2 October8am - 5pm
    Dorking TyeRoad closure with diversionsparkles.amicably.wheat to supposes.hypocrite.logbook26 - 27 September9:30am - 2:30pm
    Dorking TyeTemporary obstruction (15-min delay)rifled.potential.label to variously.kitten.disengage29 September only8am - 5pm
    B1508 St Edmunds HillRoad closure with diversionditching.transmit.investor6 - 20 October9:30am - 2:30pm
    B1068 Stoke RoadTwo-way traffic lightshaunts.vision.passwords5 - 16 October8am - 5pm

    Between now and the end of October, we need to carry out vegetation works at various locations in this area. These works are included in the table below, and also summarised here.

    Road nameType of traffic managementWhat3words
     
    Dates
     
    Timings
    Henny RoadRoad closure with diversion - see diversion route herescanty.sunflower.snacking8 - 25 September (except 15 September)24 hours a day, 7 days a week
    B1508 St Edmunds HillRoad closure with diversionditching.transmit.investor14 - 25 September9:30am - 2:30pm
    Henny Back RoadTemporary obstruction (15-min delay)otters.rocky.shuttling15 - 25 September8am – 5pm
    Lorkins LaneRoad closure with diversion - see diversion route heresocialite.slamming.caps25 September - 28 October24 hours a day, 7 days a week
    A134 Nayland RoadTwo-way traffic lightspampering.fines.standards28 - 30 September9:30am - 3pm
    B1508 St Edmunds HillRoad closure with diversionditching.transmit.investor6 - 20 October9:30am - 2:30pm
    Moat LaneRoad closure with diversion - diversion route TBCworksheet.frog.atoms1 October - 5 November24 hours a day, 7 days a week
    A134 Nayland RoadTwo-way traffic lightspampering.fines.standards21 October - 8 November (except 26 Oct)9:30am - 3pm

    Public Rights of Way

    LocationType of closureStart dateEnd Date What3Words locationDiversionTimes in PlaceNearest place
    Off Twinstead Road, LamarshClosure1 October 202629 October 2026bake.backpack.corneringDiversion map24 hoursLamarsh

    Surveys

    If a survey cannot take place on the scheduled date (due to factors such as poor weather conditions), we will endeavour to reschedule the survey in a timely manner.

    Access to land plots is agreed before any surveys take place. If you are a landowner and have questions about surveys on your land, please get in touch via your usual point of contact or the details at the bottom of the page.

    Completed works

    South of Sudbury, work to build the new Twinstead Green grid supply point (GSP) substation has been progressing well. At Bramford substation, we have built the first gantries (metal structures) that will connect the new transmission line into the substation. We’ve also been working on the foundations for the first new pylons in this area and have carried out archaeological surveys at various locations.

    Contact us

    If you have any questions or comments about the Bramford to Twinstead Reinforcement, you can get in touch by emailing [email protected], by calling 0808 196 1515, or by writing to Freepost B TO T REINFORCEMENT.

     

    What's energy resilience got to do with movie marathons?

    Find out how – and why – we’re connecting more clean energy to power the things you love.

    Find out more