What's happening now?
Our approved plans for the Bramford to Twinstead Reinforcement include:
- building approximately 18 km of new 400 kV overhead line
- building approximately 11 km of new 400 kV underground cable
- removing around 27 km of existing 132 kV and 400kV overhead line between Burstall Bridge and Twinstead Tee
- additional works to support construction, including temporary construction compounds, site offices, haul roads and new road junctions (bellmouths)
- works to deliver a minimum of 10% biodiversity net gain, including planting and other environmental enhancements.
We are also building a new substation at Twinstead Green (between Butler's Wood and Walegrave Wood). The substation is where National Grid's high voltage transmission network connects into the low voltage network run by UK Power Networks, who is the distribution network operator in this area. We applied to build the GSP substation through a separate planning application to Braintree District Council, as this will reduce the overall amount of time it will take to build the project.
You can view the detailed plans included in our application for development consent by visiting the Planning Inspectorate's website here.
Current and upcoming works
Across the first half of this year, we've focused on building construction accesses and a temporary haul road so that we can reduce the need for construction traffic to use existing roads. We’ll continue to work on these over the next few months. To do this, we’ve had to carry out vegetation management (such as trimming, pruning, coppicing or removal) at various locations. The next phase of these works is planned from mid-September until the end of October. You can read more about why we need to carry out these works here.
In the autumn, we’ll take delivery of some of the cabling that will form part of the new transmission line. We will then begin underground cable works at various locations, and construction of the new overhead line will start to ramp up.
Traffic management
When we carry out works near to or on the public highway, we often need to use traffic management (such as temporary traffic lights or road closures) to help keep you and our construction workforce safe.
To make it easier to see the works planned for your area, we have split the route of the project into four sections. In each section, a table shows the current and upcoming works for the area. These dates are subject to change, and we update these tables regularly as new works are planned.
Between now and the end of October, we need to carry out vegetation works at various locations in this area. These works are included in the table below, and also summarised here.
| Road name | Type of traffic management | What3words | Dates | Timings |
| Church Hill | Temporary Obstruction (15-min delay) | elbowing.grudging.crisper to parsnip.shelf.botanists | 14 September to 16 September | 8am - 5pm |
| A1071 Back Road | Two-way traffic lights | towers.ratio.huddling to defends.tentacle.verve | 15 September to 18 September | 8am - 5pm |
| B1070 Pipkin Hill | Two-way traffic lights | shred.brisk.sharpness | 25 September to 29 September | 9:30am - 2:30pm on weekdays, 8am - 5pm on weekends |
| Pond Hall Road | Two-way traffic lights | looks.corner.pheasants to varieties.gossiped.meaning | 14 October to 16 October | 10am - 3pm |
| Pond Hall Road | Two-way traffic lights | milder.goes.nylon to dignity.allowable.streetcar | 17 October only | 8am - 5pm |
| Pond Hall Road | Temporary Obstruction (15-min delay) | pixel.storeroom.wolf to boots.snapping.tenure | 18 - 20 October | 10am - 3pm |
| Pond Hall Road | Temporary Obstruction (15-min delay) | skies.quest.tablets to deed.truffles.bends | 23 October only | 10am - 3pm |
| Clay Lane | Road closure with diversion | punt.swatted.juicy to drummers.sunbeam.node | 26 October to 28 October | 8am - 5pm |
| Clay Lane | Temporary Obstruction (15-min delay) | punt.swatted.juicy to drummers.sunbeam.node | 29 October to 31 October | 8am - 5pm |
Between now and the end of October, we need to carry out vegetation works at various locations in this area. These works are included in the table below, and also summarised here.
| Road name | Type of traffic management | What3words | Dates | Timings |
| White Street Green | Road closure with diversion | oven.buggy.ambushes | 18 August - 18 September | 24 hours a day, 7 days a week |
| Millwood Road | Road closure with diversion | wages.winning.incurring to untruth.hedgehog.solids | 18 - 19 September | 8am – 5pm |
| White Street Green | Temporary obstruction (15-min delay) | oven.buggy.ambushes | 19 - 23 September | 8am - 5pm |
| Popes Green Lane | Road closure with diversion | incisions.grazes.chair to butchers.crystals.yard | 20 September only | 8am - 5pm |
| Millwood Road | Temporary obstruction (15-min delay) | wages.winning.incurring to untruth.hedgehog.solids | 21 September only | 8am - 5pm |
| Popes Green Lane | Temporary obstruction (15-min delay) | incisions.grazes.chair to butchers.crystals.yard | 22 September only | 8am - 5pm |
| B1070 Pipkin Hill | Two-way traffic lights | shred.brisk.sharpness | 25 - 29 September | 9:30am - 2:30pm on weekdays, 8am - 5pm on weekends |
| Holt Road | Temporary obstruction (15-min delay) | events.succeed.resembles | 28 September - 1 October | 8am - 5pm |
| Rands Road | Road closure with diversion | obvious.immunity.lads to alley.banks.mildest | 3 October only | 8am - 5pm |
| Rands Road | Temporary obstruction (15-min delay) | obvious.immunity.lads to alley.banks.mildest | 6 October only | 8am - 5pm |
| Heath Road | Road closure with diversion | nanny.dream.hardly to loved.darts.image | 8 - 18 October | 7:30am - 6:00pm |
| Rands Road | Temporary Obstruction (15-min delay) | adopts.tumble.absorbing to wobbles.smokers.drop | 12 - 16 October | 8am - 5pm |
| Heath Road | Road closure with diversion | evolving.shallower.sweated | 19 October - 15 November | 24 hours a day, 7 days a week |
Between now and the end of October, we need to carry out vegetation works at various locations in this area. These works are included in the table below, and also summarised here.
From the end of September until mid-November, we're delivering construction materials to our main construction compound, near Leavenheath. No road closures are planned as part of this work, but the delivery vehicles will be larger than normal and could therefore cause some disruption to your journey. You can read more about how these deliveries will take place here.
| Road name | Type of traffic management | What3words | Dates | Timings |
| B1508 St Edmunds Hill | Road closure with diversion | ditching.transmit.investor | 14 - 25 September | 9:30am - 2:30pm |
| High Road, Honey Tye | Road closure with diversion | markets.fend.tabs to defenders.tentacles.verve | 15 - 18 September | 8am – 5pm |
| Bures Road, Dorking Tye | Road closure with diversion | thickens.identity.boater to single.throw.intervene | 19 - 20 September | 9:30am - 2:30pm |
| High Road, Honey Tye | Temporary obstruction (15-min delay) | markets.fend.tabs to defenders.tentacles.verve | 20 September only | 8am - 5pm |
| Bures Road, Dorking Tye | Temporary obstruction (15-min delay) | thickens.identity.boater to single.throw.intervene | 21 - 22 September | 8am - 5pm |
| B1068 Stoke Road | Two-way traffic lights | haunts.vision.passwords | 24 September - 2 October | 8am - 5pm |
| Dorking Tye | Road closure with diversion | sparkles.amicably.wheat to supposes.hypocrite.logbook | 26 - 27 September | 9:30am - 2:30pm |
| Dorking Tye | Temporary obstruction (15-min delay) | rifled.potential.label to variously.kitten.disengage | 29 September only | 8am - 5pm |
| B1508 St Edmunds Hill | Road closure with diversion | ditching.transmit.investor | 6 - 20 October | 9:30am - 2:30pm |
| B1068 Stoke Road | Two-way traffic lights | haunts.vision.passwords | 5 - 16 October | 8am - 5pm |
Between now and the end of October, we need to carry out vegetation works at various locations in this area. These works are included in the table below, and also summarised here.
| Road name | Type of traffic management | What3words | Dates | Timings |
| Henny Road | Road closure with diversion - see diversion route here | scanty.sunflower.snacking | 8 - 25 September (except 15 September) | 24 hours a day, 7 days a week |
| B1508 St Edmunds Hill | Road closure with diversion | ditching.transmit.investor | 14 - 25 September | 9:30am - 2:30pm |
| Henny Back Road | Temporary obstruction (15-min delay) | otters.rocky.shuttling | 15 - 25 September | 8am – 5pm |
| Lorkins Lane | Road closure with diversion - see diversion route here | socialite.slamming.caps | 25 September - 28 October | 24 hours a day, 7 days a week |
| A134 Nayland Road | Two-way traffic lights | pampering.fines.standards | 28 - 30 September | 9:30am - 3pm |
| B1508 St Edmunds Hill | Road closure with diversion | ditching.transmit.investor | 6 - 20 October | 9:30am - 2:30pm |
| Moat Lane | Road closure with diversion - diversion route TBC | worksheet.frog.atoms | 1 October - 5 November | 24 hours a day, 7 days a week |
| A134 Nayland Road | Two-way traffic lights | pampering.fines.standards | 21 October - 8 November (except 26 Oct) | 9:30am - 3pm |
Public Rights of Way
| Location | Type of closure | Start date | End Date | What3Words location | Diversion | Times in Place | Nearest place |
| Off Twinstead Road, Lamarsh | Closure | 1 October 2026 | 29 October 2026 | bake.backpack.cornering | Diversion map | 24 hours | Lamarsh |
Surveys
If a survey cannot take place on the scheduled date (due to factors such as poor weather conditions), we will endeavour to reschedule the survey in a timely manner.
Access to land plots is agreed before any surveys take place. If you are a landowner and have questions about surveys on your land, please get in touch via your usual point of contact or the details at the bottom of the page.
Completed works
South of Sudbury, work to build the new Twinstead Green grid supply point (GSP) substation has been progressing well. At Bramford substation, we have built the first gantries (metal structures) that will connect the new transmission line into the substation. We’ve also been working on the foundations for the first new pylons in this area and have carried out archaeological surveys at various locations.
Contact us
If you have any questions or comments about the Bramford to Twinstead Reinforcement, you can get in touch by emailing [email protected], by calling 0808 196 1515, or by writing to Freepost B TO T REINFORCEMENT.
What's energy resilience got to do with movie marathons?
Find out how – and why – we’re connecting more clean energy to power the things you love.