Our approved plans for the Bramford to Twinstead Reinforcement include:

  • building approximately 18 km of new 400 kV overhead line
  • building approximately 11 km of new 400 kV underground cable
  • removing around 27 km of existing 132 kV and 400kV overhead line between Burstall Bridge and Twinstead Tee
  • additional works to support construction, including temporary construction compounds, site offices, haul roads and new road junctions (bellmouths)
  • works to deliver a minimum of 10% biodiversity net gain, including planting and other environmental enhancements.

We are also building a new substation at Twinstead Green (between Butler's Wood and Walegrave Wood). The substation is where National Grid's high voltage transmission network connects into the low voltage network run by UK Power Networks, who is the distribution network operator in this area. We applied to build the GSP substation through a separate planning application to Braintree District Council, as this will reduce the overall amount of time it will take to build the project.

You can view the detailed plans included in our application for development consent by visiting the Planning Inspectorate's website here.

Current and upcoming works

Across the first half of 2026, we have been carrying out vegetation clearance and creating new bellmouths (road junctions) so that we can build temporary haul roads for construction vehicles to use. 

Weekend working

On Saturday 4 and Sunday 5 July, works to build new bellmouth road junctions on Oak Road and Back Road (where traffic management is currently in place, as set out in the table below) will continue. Works to build new gantries within the existing boundary of Bramford substation will also continue.

Traffic management 

Full details of where we expect to implement traffic management measures can be found in the table below. These dates are subject to change, so we will update this page regularly as the works progress.

LocationTraffic management typeStart dateEnd dateWhat3Words locationDiversionTimes in placeNearest place
Layham RoadRoad closure and diversion8 June 202610 July 2026truffles.sings.panningSee map here24 hours a day, 7 days a weekLayham
Oak RoadRoad closure and diversion 17 June 202626 July 2026nowadays.hiker.drawnSee map here24 hours a day, 7 days a week Halstead
A1071 Back RoadTwo way traffic lights 22 June 202610 July 2026inflame.trifling.manifestsN/A24 hours a day, 7 days a weekHintlesham
A134 Colchester RoadTwo way traffic lights2 July 20264 July 2026offstage.strikers.sidesN/A09:00 - 16:00Assington
A134 Colchester Road/Nayland RoadTwo way traffic lights9 July 202622 July 2026pampering.fines.standardsN/A24 hours a day, 7 days a week Assington
White Street GreenTemporary obstruction (15 minute delay)14 July 202616 July 2026oven.buggy.ambushesN/A08:00 - 17:00Polstead
B1068 Stoke Road Two way traffic lights 28 July 202624 August 2026haunts.vision.passwordsN/A24 hours a day, 7 days a weekLeavenheath
B1508 St Edmunds HillTwo way traffic lights28 July 20265 August 2026ditching.transmit.investorN/A24 hours a day, 7 days a weekWorkhouse Green
A134 Colchester Road/Nayland RoadTwo way traffic lights8 August 202631 August 2026pampering.fines.standardsN/A24 hours a day, 7 days a week Assington
White Street GreenRoad closure with diversion18 August 202618 September 2026oven.buggy.ambushesTBC24 hours a day, 7 days a weekPolstead
B1508 St Edmunds HillTwo way traffic lights10 August 202623 August 2026ditching.transmit.investorN/A24 hours a day, 7 days a weekWorkhouse Green

Public Rights of Way

LocationType of closureStart dateEnd Date What3Words locationDiversionTimes in PlaceNearest place

No Public Rights of Way closures are currently in place.

Surveys

If a survey cannot take place on the scheduled date (due to factors such as poor weather conditions), we will endeavour to reschedule the survey in a timely manner.

Access to land plots is agreed before any surveys take place. If you are a landowner and have questions about surveys on your land, please get in touch via your usual point of contact or the details at the bottom of the page.

Completed works

In 2025, we carried out work to build our main construction compound off the A134, between Leavenheath and Asssington. The main construction compound is being used for site offices and for the delivery and storage of materials. The compound will be removed and the site will be restored to a condition suitable for return to its original use once construction is complete. 

At the site of our new substation, we have built a new 132 kV pylon for UK Power Networks and a temporary 400 kV pylon so that further construction activity can take place. We have also started to install electrical equipment.

Contact us

If you have any questions or comments about the Bramford to Twinstead Reinforcement, you can get in touch by emailing [email protected], by calling 0808 196 1515, or by writing to Freepost B TO T REINFORCEMENT.

 

What's energy resilience got to do with movie marathons?

Find out how – and why – we’re connecting more clean energy to power the things you love.

Find out more