What's happening now?
Our approved plans for the Bramford to Twinstead Reinforcement include:
- building approximately 18 km of new 400 kV overhead line
- building approximately 11 km of new 400 kV underground cable
- removing around 27 km of existing 132 kV and 400kV overhead line between Burstall Bridge and Twinstead Tee
- additional works to support construction, including temporary construction compounds, site offices, haul roads and new road junctions (bellmouths)
- works to deliver a minimum of 10% biodiversity net gain, including planting and other environmental enhancements.
We are also building a new substation at Twinstead Green (between Butler's Wood and Walegrave Wood). The substation is where National Grid's high voltage transmission network connects into the low voltage network run by UK Power Networks, who is the distribution network operator in this area. We applied to build the GSP substation through a separate planning application to Braintree District Council, as this will reduce the overall amount of time it will take to build the project.
You can view the detailed plans included in our application for development consent by visiting the Planning Inspectorate's website here.
Current and upcoming works
Across the first half of this year, we've focused on building construction accesses and a temporary haul road so that we can reduce the need for construction traffic to use existing roads. We’ll continue to work on these over the next few months. To do this, we’ve had to carry out vegetation management (such as trimming, pruning, coppicing or removal) at various locations. The next phase of these works is planned from mid-September until the end of October. You can read more about why we need to carry out these works here.
In the autumn, we’ll take delivery of some of the cabling that will form part of the new transmission line. We will then begin underground cable works at various locations, and construction of the new overhead line will start to ramp up.
Traffic management
When we carry out works near to or on the public highway, we often need to use traffic management (such as temporary traffic lights or road closures) to help keep you and our construction workforce safe.
To make it easier to see the works planned for your area, we have split the route of the project into four sections. In each section, a table shows the current and upcoming works for the area. These dates are subject to change, and we update these tables regularly as new works are planned.
Between now and the end of October, we need to carry out vegetation works at various locations in this area. These works are included in the table below, and also summarised here.
| Road name | Type of traffic management | What3words | Dates | Timings |
| Pond Hall Road | Two-way traffic lights | looks.corner.pheasants to varieties.gossiped.meaning | 14 - 16 October | 10am - 3pm |
| Pond Hall Road | Two-way traffic lights | milder.goes.nylon to dignity.allowable.streetcar | 17 October only | 8am - 5pm |
| Pond Hall Road | Temporary obstruction (15-min delay) | pixel.storeroom.wolf to boots.snapping.tenure | 18 - 20 October | 10am - 3pm |
| Pond Hall Road | Temporary obstruction (15-min delay) | skies.quest.tablets to deed.truffles.bends | 23 October only | 10am - 3pm |
| Clay Lane | Road closure with diversion | punt.swatted.juicy to drummers.sunbeam.node | 26 - 28 October | 8am - 5pm |
| A1071 Back Road | Two-way traffic lights | towers.ratio.huddling to defenders.tentacles.verve | 26 - 30 October | 10am - 3pm |
| Clay Lane | Temporary obstruction (15-min delay) | punt.swatted.juicy to drummers.sunbeam.node | 29 - 31 October | 8am - 5pm |
| B1070 Pipkin Hill | Two-way traffic lights | shred.brisk.sharpness | 9 - 18 November | 8am - 5pm |
Between now and the end of October, we need to carry out vegetation works at various locations in this area. These works are included in the table below, and also summarised here.
| Road name | Type of traffic management | What3words | Dates | Timings |
| Heath Road | Road closure with diversion | nanny.dream.hardly to loved.darts.image | 8 - 18 October | 7:30am - 6:00pm |
| Heath Road | Road closure with diversion | evolving.shallower.sweated | 19 October - 7 November | 24 hours a day, 7 days a week |
| Overbury Hall Road | Temporary obstruction (15-min delay) | puppets.flinches.booms | 9 - 21 November | 8am - 5pm |
| B1070 Pipkin Hill | Two-way traffic lights | shred.brisk.sharpness | 9 to 18 November | 8am - 5pm |
Between now and the end of October, we need to carry out vegetation works at various locations in this area. These works are included in the table below, and also summarised here.
From the end of September until mid-November, we're delivering construction materials to our main construction compound, near Leavenheath. No road closures are planned as part of this work, but the delivery vehicles will be larger than normal and could therefore cause some disruption to your journey. You can read more about how these deliveries will take place here.
| Road name | Type of traffic management | What3words | Dates | Timings |
| B1068 Stoke Road | Two-way traffic lights | haunts.vision.passwords | 5 - 17 October | 8am - 5pm |
| Bures Road | Road closure with diversion | helper.creamed.increases | 3 - 20 December (except 13 December) | 24 hours a day, 7 days a week |
| St Edmunds Hill | Two-way traffic lights | ditching.transmit.investor | 5 - 7 November, 29 November - 8 December and 14 - 18 December | 9am - 4pm |
Between now and the end of October, we need to carry out vegetation works at various locations in this area. These works are included in the table below, and also summarised here.
| Road name | Type of traffic management | What3words | Dates | Timings |
| Lorkins Lane | Road closure with diversion | socialite.slamming.caps | 25 September - 28 October | 24 hours a day, 7 days a week |
| Moat Lane | Road closure with diversion | worksheet.frog.atoms | 1 October - 5 November | 24 hours a day, 7 days a week |
| A134 Nayland Road | Two-way traffic lights | pampering.fines.standards | 21 October - 8 November (except 26 October) | 9:30am - 3pm |
| Cobbs Farm Chase | Road closure - access only | formal.donates.ulterior | 29 October - 27 November | 24 hours a day, 7 days a week |
| St Edmunds Hill | Two-way traffic lights | ditching.transmit.investor | 5 - 7 November, 29 November - 8 December and 14 - 18 December | 9am - 4pm |
Public Rights of Way
| Location | Type of management | Start date | End Date | What3Words location | Diversion | Times in Place | Nearest place |
| Off Twinstead Road, Lamarsh | Closure | 1 October 2026 | 31 October 2026 | pizza.badminton.shrub | Diversion map | 24 hours | Lamarsh |
Underground cable works in Dedham Vale
September 2026 to June 2027
National Grid is beginning the main construction phase of the Bramford to Twinstead Reinforcement. As part of these works, we need to install a new 400 kV underground cable in the Dedham Vale area. This involves digging trenches and installing ducts along the cable route. Once this work is complete, trenches will be backfilled and we will restore the areas we’ve used.
During the works, where the cable route crosses a road, we’ll need to dig a trench and install the cable ducts beneath it. This will require some temporary road closures. We have applied for the necessary permits and are currently planning traffic management measures for November 2026. We’ll share confirmed closure details and diversion routes before they take effect, so you can plan your journey. You can see all upcoming closures in the dropdowns in the Traffic management section on this page. We apologise for any inconvenience this may cause.
We’ll carry out the work within the construction hours as outlined in the Development Consent Order (DCO) for the project. We will manage works to reduce disruption where we can.
You can find out more about how we lay underground cables in this video here.
River Box Horizontal Directional Drilling (HDD)
28 September 2026 to January 2027
As part of the main construction phase of the Bramford to Twinstead Reinforcement, we’re also preparing to install ducts for the new 400 kV underground cable beneath the River Box. To do this, we will use horizontal directional drilling, which means we can drill under the river rather than dig through it. This approach reduces disturbance at the surface and avoids digging directly in the watercourse. The crossing beneath the river will be approximately 100 metres long.
We’ll set up temporary work areas on either side of the crossing to allow us to dig entry and exit pits, drill beneath the river and install the ducts. We’ll also remove and restore the temporary work areas after the relevant work is complete, in accordance with the project’s approved requirements.
The site entrances are already in place, so we do not expect to need traffic management for access to this work. We’ll carry out the work within the construction hours outlined in the Development Consent Order (DCO) for the project and will let people know in advance if activities may affect local access or cause disruption.
You can find out more about how we drill under rivers and roads in this video here.
Surveys
If a survey cannot take place on the scheduled date (due to factors such as poor weather conditions), we will endeavour to reschedule the survey in a timely manner.
Access to land plots is agreed before any surveys take place. If you are a landowner and have questions about surveys on your land, please get in touch via your usual point of contact or the details at the bottom of the page.
Completed works
South of Sudbury, work to build the new Twinstead Green grid supply point (GSP) substation has been progressing well. At Bramford substation, we have built the first gantries (metal structures) that will connect the new transmission line into the substation. We’ve also been working on the foundations for the first new pylons in this area and have carried out archaeological surveys at various locations.
Contact us
If you have any questions or comments about the Bramford to Twinstead Reinforcement, you can get in touch by emailing [email protected], by calling 0808 196 1515, or by writing to Freepost B TO T REINFORCEMENT.
What's energy resilience got to do with movie marathons?
Find out how – and why – we’re connecting more clean energy to power the things you love.