What's happening now?

Our approved plans for the Bramford to Twinstead Reinforcement include:

  • building approximately 18 km of new 400 kV overhead line
  • building approximately 11 km of new 400 kV underground cable
  • removing around 27 km of existing 132 kV and 400kV overhead line between Burstall Bridge and Twinstead Tee
  • additional works to support construction, including temporary construction compounds, site offices, haul roads and new road junctions (bellmouths)
  • works to deliver a minimum of 10% biodiversity net gain, including planting and other environmental enhancements.

We are also building a new substation at Twinstead Green (between Butler's Wood and Walegrave Wood). The substation is where National Grid's high voltage transmission network connects into the low voltage network run by UK Power Networks, who is the distribution network operator in this area. We applied to build the GSP substation through a separate planning application to Braintree District Council, as this will reduce the overall amount of time it will take to build the project.

You can view the detailed plans included in our application for development consent by visiting the Planning Inspectorate's website here.

Current and upcoming works

Across the first half of this year, we've focused on building construction accesses and a temporary haul road so that we can reduce the need for construction traffic to use existing roads. We’ll continue to work on these over the next few months. To do this, we’ve had to carry out vegetation management (such as trimming, pruning, coppicing or removal) at various locations. The next phase of these works is planned from mid-September until the end of October. 

In the autumn, we’ll take delivery of some of the cabling that will form part of the new transmission line. We will then begin underground cable works at various locations, and construction of the new overhead line will start to ramp up.

Traffic management 

Full details of where we expect to implement traffic management measures can be found in the table below. These dates are subject to change, so we will update this page regularly as the works progress.

LocationTraffic management typeStart dateEnd dateWhat3Words locationDiversionTimes in placeNearest place
White Street GreenRoad closure with diversion18 August 202618 September 2026oven.buggy.ambushesSee map here24 hours a day, 7 days a weekPolstead
Cripple CornerRoad closure with diversion17 August 202620 September 2026lure.bucket.detonatedSee map here24 hours a day, 7 days a week Pebmarsh
Henny RoadRoad closure with diversion8 September 202625 September 2026scanty.sunflower.snackingSee map here24 hours a day, 7 day a weekLamarsh
B1508 St Edmunds HillRoad closure with diversion14 September 202625 September 2026ditching.transmit.investorTBC09:30 - 14:30Workhouse Green
A1071 Back RoadTwo way traffic lights15 September 202618 September 2026towers.ratio.huddling to variety.shirtless.januaryN/A08:00 - 17:00Hintlesham
Henny Back RoadTemporary obstruction (15 minute delay)15 September 202625 September 2026otters.rocky.shuttlingN/A08:00 - 17:00Alphamstone
Millwood RoadRoad closure with diversion18 September 202619 September 2026wages.winning.incurring to untruth.hedgehog.solidsTBC08:00 - 17:00Polstead Heath
White Street GreenTemporary obstruction (15 minute delay)19 September 202623 September 2026oven.buggy.ambushesN/A08:00 - 17:00Polstead
High RoadTemporary obstruction (15 minute delay)20 September 202620 September 2026markets.fend.tabs to defenders.tentacles.verveN/A08:00 - 17:00Honey Tye
Millwood RoadTemporary obstruction (15 minute delay)18 September 202619 September 2026wages.winning.incurring to untruth.hedgehog.solidsN/A08:00 - 17:00Polstead Heath
Bures RoadTemporary obstruction (15 minute delay)21 September 202622 September 2026thickens.identity.boater to single.throw.interveneN/A08:00 - 17:00Dorking Tye
Popes Green LaneTemporary obstruction (15 minute delay)22 September 202622 September 2026incisions.grazes.chair to butchers.crystals.yardN/A08:00 - 17:00Polstead Heath
B1068 Stoke RoadTwo way traffic lights24 September 20262 October 2026haunts.vision.passwordsN/A08:00 - 17:00Stoke-by-Nayland
Church HillTemporary obstruction (15 minute delay)28 September 202628 September 2026elbowing.grudging.crisper to parsnip.shelf.botanistsN/A08:00 - 17:00Burstall
Holt RoadTemporary obstruction (15 minute delay)28 September 20261 October 2026events.succeed.resemblesN/A08:00 - 17:00Polstead Heath
Dorking TyeTemporary obstruction (15 minute delay)29 September 202629 September 2026rifled.potential.label to variously.kitten.disengageN/A08:00 - 17:00Dorking Tye
Rands RoadTemporary obstruction (15 minute delay)6 October 20266 October 2026obvious.immunity.lads to alley.banks.mildestN/A08:00 - 17:00Layham
B1508 St Edmunds HillRoad closure with diversion6 October 202620 October 2026ditching.transmit.investorTBC09:30 - 14:30Workhouse Green
Pond Hall RoadTemporary obstruction (15 minute delay)23 October 202623 October 2026skies.quest.tablets to deed.truffles.bendsN/A10:00 - 15:00Hadleigh
Clay LaneTemporary obstruction (15 minute delay)29 October 202631 October 2026punt.swatted.juicy to drummers.sunbeam.nodeN/A08:00 - 17:00 Hadleigh

 

Public Rights of Way

LocationType of closureStart dateEnd Date What3Words locationDiversionTimes in PlaceNearest place

No Public Rights of Way closures are currently in place.

Surveys

If a survey cannot take place on the scheduled date (due to factors such as poor weather conditions), we will endeavour to reschedule the survey in a timely manner.

Access to land plots is agreed before any surveys take place. If you are a landowner and have questions about surveys on your land, please get in touch via your usual point of contact or the details at the bottom of the page.

Completed works

South of Sudbury, work to build the new Twinstead Green grid supply point (GSP) substation has been progressing well. At Bramford substation, we have built the first gantries (metal structures) that will connect the new transmission line into the substation. We’ve also been working on the foundations for the first new pylons in this area and have carried out archaeological surveys at various locations.

Contact us

If you have any questions or comments about the Bramford to Twinstead Reinforcement, you can get in touch by emailing [email protected], by calling 0808 196 1515, or by writing to Freepost B TO T REINFORCEMENT.

 

What's energy resilience got to do with movie marathons?

Find out how – and why – we’re connecting more clean energy to power the things you love.

Find out more