In England and Wales, energy projects over 50 MW* typically connect to the transmission network via substations. These connections are made through designated “bays.” Large electricity users, such as data centres and factories, may also connect at a transmission level. 

However, not all substations have spare capacity. If space and system conditions allow, substations can be extended to add new bays. National Grid Electricity Transmission (NGET) will construct the substation extension, while the customer is responsible for building their own bay.

The 200-tonne transformer will be transported to Overton Substation, completing delivery of all eight supergrid transformers to the new substations at Overton and Monk Fryston. 

The transformer will be transported by a specialist delivery vehicle from Teesport Docks, in Middlesbrough, over 50 miles via the highway network to our substation on Overton Road. The delivery route will follow the A19, through villages including Birdforth, Thormanby and Shipton by Beningbrough before turning onto Overton Road where the Overton Substation is located. 

Connection outage scheduling


What are connection outages and how are they scheduled?

As the Transmission Owner for England and Wales, we are key to connecting a variety of assets to the high voltage network. Before a customer is ready to connect, certain processes must be followed to ensure the safe operation of the network and surrounding equipment.

To ensure the safety of our workforce and the public while this is carried out, traffic management measures are expected to be in place between 17 and 21 October 2025. These will operate between 08:00 and 17:30. Outside of these hours, the traffic management will be removed. The work will be carried out by Balfour Beatty, on behalf of National Grid.

During the times outlined above, temporary traffic lights will be in place. Advance warning signs have been displayed, and the work areas will be clearly marked with cones and barriers.

  • Public consultation launched on Cross Border Connection, a major new electricity project in Cumbria
  • Part of The Great Grid Upgrade, which is growing the UK’s electricity network
  • Plans include a new overhead power line and substation in the Carlisle area to meet rising energy demand and d

To ensure the safety of our workforce and the public while this is carried out, traffic management measures are expected to be in place between 14 and 24 October 2025. These will operate between 08:00 and 17:30. Outside of these hours, the traffic management will be removed. The work will be carried out by Balfour Beatty, on behalf of National Grid.

Subscribe to