Nailsea to Tickenham

Current construction activity

Date fromDate toActivity
May 20212024Building and energising new T-pylons
20202024Removing existing pylons
2018OngoingRoadworks and traffic management
2018OngoingAccess to public footpaths and rights of way

 

Overview – Autumn 2024

National Grid is moving into the final stage for completing the northern section of the Hinkley Connection route between Sandford and Seabank substations, which passes to the west of Nailsea and the east of Tickenham village. 

The main works currently in this area is the removal of  construction accesses, temporary roads, and work areas built to construct the new overhead line. You may notice more construction traffic on local roads. We will keep you informed about any required traffic management updates in advance. 

The construction of 68 new T-pylons between Sandford substation and Portbury, including the hanging of the conductors - or wires - is complete. 

The T-pylons have been connected to the new line of 27 lattice pylons running from the Bristol Port area, across the River Avon and into Seabank substation in Avonmouth. Our teams will now test and prepare to commission and energise the new line between Sandford and Seabank, which is planned to take place in 2025.

Using the T-pylon design, reduces the height of the new electricity infrastructure by a third. At 35 metres high, the new T-pylons are shorter and take up far less room on the land than National Grid's traditional lattice transmission pylons. 

To make way for the new 400,000 volt connection, National Grid has removed 249 lower voltage lattice pylons, and overhead wires stretching 67 kilometres from the Somerset landscape. 

Thank you from everyone working on the project for your patience and understanding as we work to toward completion. This project will play a key role in helping the UK meet its net zero ambitions by transmitting cleaner, homegrown, energy around the UK – enough to power six million homes and businesses.

Register to receive project updates direct to your inbox

Take a look at our detailed map

Nailsea to Tickenham timeline

Completed late 2021

 

Undergrounding the 132,000 volt overhead line between Nailsea and Portishead substation

This work has been completed. 

Work carried out:

  • Built temporary entrances and access roads to allow construction traffic to enter site from the local highway. You can find more information on our construction information page.

  • Built temporary construction compounds.

  • Built an underground cable between Nailsea and Portishead substation.

  • Built a pylon to connect the existing overhead line at Nailsea to the new underground cable.

The new underground cable section was built as a direct result of feedback received during our consultation. Now operational, it will enable us to completely remove the existing 132,000 volt overhead line between Nailsea and Portishead substation that currently runs very close to people’s properties

Mid 2021 to mid 2024

 

Build new 400,000 volt overhead line

What we're doing:

  • In this area, to minimise disruption, we will be sharing temporary construction compounds and temporary entrances and access roads built for other elements of the build.

  • Building a new overhead line from Sandford substation to Seabank substation (approximately 31.2 km).

  • We will use T-pylons in this area.

Mid 2021 to mid 2024

 

Remove existing 132,000 volt overhead lines

What we're doing:

  • Removing approximately 9 km of existing overhead line between Nailsea and Portishead substation that currently runs very close to people’s properties. We are removing this as a direct result of feedback received during our consultation.

  • Removing existing overhead line from the A368 in Sandford to Avonmouth, which will make way for, and minimise the visual impact of, the new connection.