Date from | Date to | Activity |
May 2020 | Ongoing | T-pylons and reinstatement between Bridgwater substation and Loxton |
May 2020 | Ongoing | Access to public footpaths and rights of way |
2018 | Ongoing | Roadworks and traffic management |
The new T-pylons between Bridgwater and Loxton are now energised and transporting electricity around the National Grid electricity network.
To make way for the new 400,000 volt connection, National Grid has removed 249 lower voltage lattice pylons, and overhead wires stretching 67 kilometres from the Somerset landscape.
We’ve removed 99 pylons between Bridgwater and Sandford, leaving part of Mendip Hills National Landscape pylon free for the first time in almost 100 years.
Work is ongoing to remove temporary haul roads, road accesses and culverts that were built to construct the T-pylons and reinstate the land.
Thank you from everyone working on the project for your patience and understanding as we progress with this important work to connect six million homes and businesses to new sources of homegrown, low carbon energy, and help the UK meet its net zero ambitions.
What we're doing:
Building two temporary construction compounds and a temporary entrance and access road off the A38, north of Tarnock, to allow construction traffic to enter the site from the local highway. Work will start on the access and compounds in 2019.
One of the compounds will includes site offices and internal and external storage facilities to support the work to build a 400,000 volt underground cable across the Mendip Hills Area of Outstanding Natural Beauty (AONB).
The other temporary site compound will be used for the construction of the 400,000 volt overhead line and removal of the existing 132,000 volt overhead line in the area.
This work has been completed
Work carried out:
Built a new overhead line from the existing Hinkley to Melksham overhead line, which is north of Woolavington, northwards to a new cable sealing end (CSE) compound just south of the Mendip Hills. See Mendip Hills for further information about the CSE compound.
We will use T-pylons in this area, with the exception of where the overhead line connects to the existing overhead line.
This work has been completed.
Work carried out:
Removed existing overhead line from Bridgwater substation to the A368 in Sandford. This made way for, and minimised the visual impact of the new overhead line.