The Willesden and Kensal Green Connection project comprises two phases. The first phase of the project was completed in May 2025.

The second phase of works involved installing new cables along the canal towpath. This phase began in July 2025 and saw the installation of new equipment and cables to run the cable along the canal. Our teams also planted new hedgerows along the towpath.

Pontoons were used during phase one, but this was not possible during the second phase of works. The cable installation moved along the towpath meaning lengthy sections of the Grand Union Canal towpath needed to be closed while work took place. 

Diversions

Following a change to the works programme, the second phase of our works are on hold. The third closure planned between Barretts Green Road and Old Oak Lane is expected to take place in 2026 and confirmed dates will be shared in due course. 

Community engagement

In June 2025, we hosted community drop-ins and a webinar to provide information and address questions ahead of our phase two works, and answered any questions regarding the project.

Details and timings of the events that took place in June can be found below:

Event type

Date

Time

Location

Online webinar

Tuesday 10 June

6-7pm

Online

Pop-up event

Tuesday 17 June

 

5-7pm

Entrance to Sainsbury’s

canal side at Ladbroke Grove

Pop-up event

Wednesday 18 June

5-7pm

Outside The Collective

Pop-up event

Thursday 19 June

5-7pm

The canal access on Barretts Green Road

In-person drop in

28 June 2025

10am-2pm

Queens Park Court Community Hall, Droop St, London W10 4QD


 

Have a query? 

Find out more about this project or receive updates on its progress.

Submit your details