Overview
Pelham substation will be expanded to enable the delivery of two new quad booster units north east and south west of the site. These quad boosters will help control the flow of electricity through the network, balancing power supply between different transmission lines and ensuring electricity can be directed where it's needed most.
Initial enabling works have been undertaken to make way for the new quad boosters, with their arrival scheduled for early 2026. Enabling works are preparatory activities such as vegetation clearance, fencing installation, temporary access tracks, and scaffolding construction. These steps are necessary before the main substation upgrades and overhead line improvements can begin.
To facilitate new connections, the substation will also see some diversions, relocations and reconfiguring of existing overhead Line OHL and towers. This has the capacity to streamline the current tower configuration around the site and improve some visual impacts.
The arrival of the quad booster units in 2026 will require road closures across a two-week period. The details of these will be agreed with the local highways authority and will seek to minimise day-to-day impacts as much as possible. The works undertaken fall within permitted development, rather than the remit of the consented 2014 Development Consent Order (DCO). As part of the works, we are looking at where improvements can be made to the natural landscape to enhance walking routes and deliver a minimum 10% biodiversity net gain.
For the latest updates on work in these areas, click on the relevant location below:
Timeline
February – September 2024 | Enabling works at Pelham substation. Enabling works are preparatory activities such as vegetation clearance, which is necessary before the main substation upgrades can begin. |
2025 – 2027 | Reconductoring of overhead line (OHL) between Pelham and Waltham Cross |
2026 | Vegetation clearance and delivery of quad booster units to Pelham substation |
Address
Pelham Substation, Stocking Pelham, Bishop's Stortford, SG9

Community involvement
We are committed to engaging with communities to ensure the projects deliver other localised benefits, including social benefits via our Community Grant Programme and environmental benefits via biodiversity net gain (i.e., increasing biodiversity in the area we are operating in above what is currently there).
The Community Grant Programme is run by the National Grid Electricity Transmission (NGET) business. The programme is aimed at community organisations and charities in areas where our work is impacting local people through our operations and construction activities.
Communities impacted by the maintenance of existing infrastructure (e.g. refurbishment of overhead lines or substations resulting in road closures and other impacts) can apply for grants of up to £10,000.
You can read more about the Community Grant Programme here: https://www.nationalgrid.com/responsibility/community/community-grant-programme.
Contact us
If you would like any further information or to speak to a member of the community relations team about the works, please use the contact form on our website or via the contact details below.
Email: [email protected]
Phone: 0800 279 3408