Construction has now begun, with new infrastructure expected to be operational in 2027 and final works and reinstatement anticipated to be complete by the end of 2028.
Construction work will be phased across the different areas which form Yorkshire GREEN. You can find out more about the work happening in different areas by looking at our interactive map.
Morrison Energy Services (MES) has been selected to deliver the new overhead line and existing overhead line refurbishment; Murphy Power Networks (Murphy) will deliver two new substations in Overton and Monk Fryston; and Hyosung and Hyundai will supply transformers to the substations and cable sealing end compounds (a component that joins underground cables with overhead lines).
We are working very closely with our contractors to communicate the work they are undertaking.
Preparatory works for Yorkshire GREEN have progressed well since they began in autumn 2024 and we would like to thank you for your patience and cooperation while we have been undertaking these works.
We are pleased to report that the National Cycle Network Route 65 diversion between Overton Road and Station Lane is now open and will remain in place throughout the construction period.
We will carry on with our preparatory works for the first few months of 2025. These will enable us to begin the main works in spring 2025.
We will continue with our preparatory works for the first few months of 2025, our preparatory works will include:
Our team are doing all they can to minimise any inconvenience caused by our works, however, given the nature of the activity, it is likely that there will continue to be some disruption in areas we are carrying out our works.
To ensure the safe and timely completion of our preparatory works, we will need to put some traffic management measures in place around the areas we are working in. You can also view upcoming and existing traffic management on our interactive map.
These include:
Corban Lane, Shipton – Monday 10 March until Monday 24 March 2025
To allow us to construct our access track to the field we are working within, there is a lane closure in place on Corban Lane, Shipton near the entrance to Newlands Farm.
The lane closure will be in place between Monday 10 March until Monday 24 March 2025 from 7am and 7pm Monday to Friday.
Temporary traffic lights are in place to maintain two-way traffic flow. Outside of these hours the lane closure will be removed, if safe to do so. There may be occasions when the lane closure will need to stay in place to ensure the safety of all road users. We will also open the road if the closure is not needed on a particular day.
Newthorpe Lane, B1222, Sherburn in Elmet – Monday 10 March until Monday 24 March 2025
To allow us to construct our access track to the field we are working within, there is a lane closure on Newthorpe Lane, B1222, Sherburn in Elmet at the junction with Hall Lane.
The lane closure will be in place between Monday 10 March until Monday 24 March 2025 from 7am and 7pm Monday to Friday.
Temporary traffic lights are in place to maintain three-way traffic flow. Outside of these hours the lane closure will be removed, if safe to do so. There may be occasions when the lane closure will need to stay in place to ensure the safety of all road users. We will also open the road if the closure is not needed on a particular day.
Marston Lane, Hessay – Monday 24 March until Sunday 6 April 2025
To allow us to construct a bellmouth to the field we are working within on Marston Lane, we need to close Marston Lane to vehicles and other road users, near to the junction with the A59.
We are expecting this closure to be in place for two weeks from Monday 24 March until Sunday 6 April 2025.
The road closure is expected to be in place from 7am to 7pm on weekdays, and 8am to 5pm on weekends. Outside these hours, if safe to do so, the road closure will be removed, and all road users will be able to travel along the road as normal.
B1217, Saxton – Monday 24 March until Monday 7 April 2025
From Monday 24 March until Monday 7 April 2025, there will be a lane closure in place on the B1217, near where Dam Lane meets the B1217.
This closure is required to enable works to upgrade pylon foundations.
The lane closure will be in place at all times, for the duration of the closure period. Temporary traffic lights will be in place to maintain two-way traffic flow.
A63, Monk Fryston – Friday 28 March until Monday 28 April 2025
To enable us to construct our bellmouths, we will need to close a short section of the A63 in one direction at a time, near Selby Fork Interchange, during ‘off peak’ hours from 9am to 3pm each day.
We are expecting this closure to be in place from Friday 28 March until Monday 28 April 2025. Temporary traffic lights will be in place from 9am to 3pm each day to maintain two-way traffic flow. Outside of these hours, the lane closure and temporary traffic lights will be removed, if safe to do so.
The lane closure will begin on the northbound side (towards Monk Fryston) and will then swap to the southbound side (towards Selby Fork Interchange).
Westfield Lane, South Milford - Monday 7 April until Tuesday 22 April 2025
We need to construct our access point to the field we will be working within on Westfield Lane. To enable us to construct the bellmouth, we will need to close Westfield Lane to vehicles and other road users near the junction with Whin Lane for two weeks from Monday 7 April to Tuesday 22 April 2025.
The road closure is expected to be in place between 7am to 7pm on weekdays. We do not anticipate needing to carry out work at the weekend, but if we do this will take place between 8am and 5pm. Outside these hours, if safe to do so, the road closure will be removed, and all road users will be able to travel along the road as normal.
A59, Hessay - Tuesday 29 April until Tuesday 13 May 2025
To enable our teams to construct and widen the bellmouth to the field we will be working in off the A59, we need to close a short section of the A59 in the eastbound direction, near Marston Lane during ‘off-peak’ hours from 9am to 3pm each day.
To ensure vehicle movement is maintained, two-way temporary traffic lights will be in place from 9am to 3pm each day. We are expecting this closure to be in place between Tuesday 29 April until Tuesday 13 May 2025.
If you live in the Overton and Monk Fryston areas, you may have already noticed vehicles in the area delivering stone to our compounds. From Thursday 2 January 2025, the number of these deliveries to our site will increase for a period of between six to eight weeks. To minimise inconvenience, we are:
Given there may be some delays as a result of more vehicles on the road, we would encourage you to plan your journeys ahead and/or use an alternative route to make sure you can reach your destination on time.
If you experience any issues while stone deliveries are ongoing, please get in touch with our Community Relations Team.
If you have a question, you can contact us in the following ways:
Email us: [email protected]
Call our Freephone number: 0800 029 4359
Write to us: FREEPOST Yorkshire GREEN (please note that you do not need a stamp)
What's energy resilience got to do with movie marathons? Find out how – and why – we’re connecting more clean energy to power the things you love.
Find out more