Our proposals

The key onshore and marine elements of our proposals in England and English waters are: 

  • Subsea high voltage direct current (HVDC) cables. In English waters, EGL 3's cable would be approximately 436 km long and EGL 4's would be approximately 425 km
  • Transition joint bays to connect our subsea and onshore HVDC cables, located onshore near to our proposed cables landfall north of Anderby Creek on the Lincolnshire coastline
  • Underground HVDC cables running together for approximately 100 km from the joint landfall north of Anderby Creek to the EGL 3 and EGL 4 converter stations in the Walpole area, West Norfolk
  • Two converter stations in the Walpole area with one converter station for EGL 3 and one for EGL 4
  • One substation in the Walpole area, called Walpole B, where both EGL 3 and EGL 4’s Walpole converter stations would connect to and then onto the electricity transmission network (this substation is also jointly proposed as part of NGET's Grimsby to Walpole project)
  • Onshore underground high voltage alternating current (HVAC) cables that would connect the converter stations into the substation
  • Supplementary works to the existing 400 kV overhead line to enable a connection with the new Walpole substation. 

Sufficient land would be required to build EGL 3 and EGL 4 and to reduce the potential impacts of the projects, including: 

  • temporary land for construction activities including work areas for construction equipment and machinery, site offices, welfare, storage, access and drainage
  • land required for mitigation, compensation and enhancement of the environment as a result of the environmental assessment process, and for the purposes of delivering biodiversity net gain, for example by landscaping and planting. 

Find out where our proposals would be located

You can view our onshore proposals from the second stage of consultation on our interactive map by following the link below. 

To learn more about what’s being proposed in your area, please see our Document library. This includes the materials we have published on the EGL 3 and EGL 4 projects, including the Stage 2 consultation document which provides more detail and information on our proposals. 

Interactive map

EGL 3 and EGL 4 onshore in England

Image
EGL3&4 Connection Diagram

 

EGL 3 and EGL 4’s timeline

Image
EGL34 timeline

 

What’s happened so far?

In spring 2024, we held our Stage 1 consultation on our early proposals for EGL 3 and EGL 4. Feedback from this consultation helped to develop our proposals.

During our Stage 2 consultation, held between May and June 2025, we presented and sought feedback on our detailed proposals for EGL 3 and EGL 4.

The feedback received during Stage 2 consultation helped us to further develop our plans and identify some additional land required to build the Projects.

We held a targeted consultation in spring 2026 to gather feedback on proposed works within the additional land identified during the second stage of consultation. Feedback from our consultations, alongside our ongoing technical and environmental work, helped us to finalise our proposals.

In October 2026, we submitted our Development Consent Order (DCO) application for EGL 3 and EGL 4 to the Planning Inspectorate. The Planning Inspectorate is currently reviewing our application and will decide whether to accept it for examination.