We need to do additional work in some areas as part of the Yorkshire GREEN Project to ensure that the network can manage the additional energy flows.
These areas are presented as Sections A, C and E within our consultation plans, as shared during our Statutory Consultation in 2021, which provide a detailed overview of the existing infrastructure that will be improved or replaced in these areas. Each section has been split into sheets (or maps) with 17 sheets in total across these geographical areas.
We need to install additional equipment at the Osbaldwick substation, including an isolator (a safety device which disconnects a circuit from electrical supply) and a circuit breaker (a switch which manages and protects power flow). We would also need to build and dismantle an existing gantry, build a new gantry and section of cable at this substation. All construction works, including the construction of any temporary compounds, would take place within the existing operational land at Osbaldwick substation.
*Please note that the above proposals are shown as they were presented during our statutory consultation in 2021.
We need to carry out upgrading works to the existing 275kV Poppleton to Monk Fryston XC/XCP overhead line route to accommodate the new sections of overhead lines, as set out in the previous sections. Works along this route would involve replacing the conductors (overhead wires) and fittings. Here we are increasing the number of conductors from single to twin, doubling the number of wires on each arm of the pylon to allow the overhead line to transport more power.
*Please note that the above proposals are shown as they were presented during our statutory consultation in 2021.
Proposals for the North west of York area (Section B).
Proposals for the Tadcaster area (Section D).
Proposals for the Monk Fryston substation area (Section F).
Get in touch with the Yorkshire GREEN project team.