- Back
- Connections
- Engineering Solutions
- Network and infrastructure
- Innovation
- Pathway to net zero
- Who we are
- Contact us
Date from | Date to | Activity |
May 2021 | 2024 | |
2020 | 2024 | Removing existing pylons |
2018 | Ongoing | |
2018 | Ongoing | Access to public footpaths and rights of way |
National Grid is moving into the final stage for completing the north section of the Hinkley Connection route between Sandford and Seabank substations.
The 68 T-pylon structures between Sandford substation and Portbury were completed, with the final diamond shaped insulators lifted into place on a pylon between Yatton and Kenn in July 2023.
The innovative T-pylons will soon join the new line of 27 lattice pylons erected between the River Avon and Seabank substation. The combined total of 95 new pylons will be energised by the end of 2024. Before then, the last section of conductors will be hung from the T-pylons between the west end of Nailsea and Tickenham.
Using the T-pylon design, reduces the height of the new infrastructure by a third. At 35 metres high they are shorter than National Grid's traditional lattice transmission pylons and take up far less room on the land.
To make way for the new connection route, we are removing 249 existing 132,000 volt lattice pylons and overhead wires stretching 67 kilometres from the Somerset landscape. 99 percent of the lattice pylons have now been removed, including the last of the remaining pylons within Portbury Wharf Nature Reserve.
Reinstatement of the land along the connection route is underway and will continue through to 2025.
Thank you from everyone working on the project for your patience and understanding as we work to towards full completion of this project which will play such a key role in helping the UK meet its net zero ambitions by transmitting cleaner, homegrown, energy around the UK – enough to power 6 million homes and businesses.
This work has been completed.
Work carried out:
Built temporary entrances and access roads to allow construction traffic to enter site from the local highway. You can find more information on our construction information page.
Built temporary construction compounds.
Built a 132,000 volt underground cable between Nailsea and Portishead Substation.
Built a new CSE pylon to connect the existing overhead line at Nailsea to the new underground cables.
This new underground cable section has been built as a direct result of feedback received during our consultation. It will enable us to completely remove the existing 132,000 volt overhead line that currently runs very close to people’s properties.
What we're doing:
In this area, to minimise disruption, we will be sharing temporary construction compounds, and temporary entrances and access roads built for other elements of the build.
Building a new 400,000 volt overhead line from Sandford Substation to Seabank Substation (approximately 31.2km).
We will use T-pylons in this area.
What we're doing:
Removing approximately 9 km of existing overhead line between Nailsea and Portishead substation that currently runs very close to people’s properties. We are removing this as a direct result of feedback received during our consultation.
Removing overhead line from the A368 in Sandford to Avonmouth, which will make way for, and minimise the visual impact of the new connection.
What we're doing:
Making changes to the inside of Portishead Substation to enable the connection of the new 132,000 volt underground cable from Nailsea.
Building a temporary construction compound to the east of the substation.
Building temporary entrances and access roads to allow construction traffic to enter the undergrounding site from the local highway. You can find more information on our construction information page.
Removing a section of 132,000 volt overhead line to the east of the substation and replacing it with underground cable. This will enable the 400,000 volt overhead line to pass safely overhead.
Installing a Cable Sealing End (CSE) pylon to connect the new underground cable to the existing overhead line.