Date from | Date to | Activity |
October 2021 | 2024 | Removing existing pylons |
May 2020 | Ongoing | T-pylons and reinstatement between Bridgwater substation and Loxton |
January 2023 | 2024 | Connecting T-pylons to the existing network |
May 2020 | Ongoing | Access to public footpaths and rights of way |
2018 | Ongoing | Roadworks and traffic management |
The new T-pylons between Bridgwater and Loxton are energised and transporting electricity around the National Grid electricity network.
To make way for the new 400,000 volt connection, National Grid has removed 249 lower voltage lattice pylons, and overhead wires stretching 67 kilometres across the Somerset landscape.
A Horsey levels, north of Bridgwater we are currently working to connect the southernmost section of new 400,000 volt T-pylons with the existing overhead line that we have upgraded between Shurton and Horsey via a new nine-armed junction pylon.
To free up space for that overhead line connection, a section of new underground cable has been installed and energised connecting Shurton substation to Bridgwater substation.
Work is ongoing to remove temporary haul roads, road accesses and culverts that were built to construct the T-pylons and reinstate the land.
Thank you from everyone working on the project for your patience and understanding as we progress with this important work to connect six million homes and businesses to new sources of homegrown, low carbon energy, and help the UK meet its net zero ambitions.
Register to receive project updates direct to your inbox.
Take a look at our detailed map
This work has been completed.
Work carried out:
Built a new overhead line from the existing Hinkley to Melksham overhead line, which is north of Woolavington, northwards to a new cable sealing end (CSE) compound just south of the Mendip Hills. See Mendip Hills for further information about the CSE compound.
Built temporary entrances and access roads to allow construction traffic to enter site from the local highway. You can find more information on our construction information page.
In this area, contractors used the temporary construction compound built north of Tarnock.
We will use T-pylons in this area, with the exception of where the overhead line connects to the existing overhead line.
This work has been completed.
Work carried out:
Removed existing overhead line from Bridgwater substation to the A368 in Sandford. This made way for, and minimised the visual impact of the new overhead line.
What we're doing:
We are upgrading the wires on the existing pylons.
What we're doing:
Building a new overhead line between the existing Hinkley to Bridgwater overhead line on Horsey Level and the existing Hinkley to Melksham overhead line which is north of Woolavington.
Building temporary entrances and access roads to allow construction traffic to enter site from the local highway. You can find more information on our construction information page.
In this area, contractors will use the temporary construction compound built north of Tarnock.
We will use T-pylons in this area, with the exception of where the overhead line connects to existing overhead lines. When complete, this will become the new Shurton to Melksham overhead line.
What we're doing:
Installing new electrical equipment, which is required as part of the upgrading of the existing Hinkley to Bridgwater overhead line.
This work is being carried out within the existing substation boundary and does not require planning permission.
This is the point at which the new overhead line connects to the existing Hinkley to Bridgwater overhead line on Horsey Level.
What we're doing:
Building a temporary construction compound, and entrance and access road to allow construction traffic to enter site from the A39 Bath Road. You can find more information on our construction information page.
Connecting the new overhead line to the existing Hinkley to Bridgwater overhead line on Horsey Level.
Removing a small section of the existing Hinkley to Bridgwater overhead line and replacing it with an underground cable. This will enable the overhead line to pass overhead.
Building two cable sealing end (CSE) compounds (approximately 34m by 30m) at either end of the underground cable to connect it to the existing overhead line.