The 29m high gasholder in Great Yarmouth has been part of the town’s skyline since it was built in 1884. However, specialist condition assessments show that works are needed to secure the long term future of this Grade II Listed structure. 

Following extensive consultation with the local community and Historic England, National Grid’s plan for the site was given planning permission and listed building consent by Great Yarmouth Borough Council in April 2024. National Grid owns the former gasworks site at Admiralty Road, but gasholders are no longer used as part of the national gas system. 

National Grid has a national programme agreed with OFGEM to bring redundant sites such as these back into use, but the Grade II Listed status of the Victorian gasholder and its condition requires a different approach. Following detailed technical assessments it was agreed that the tank at the bottom of the gasholder should be removed and the large visible frame should then be refurbished in-situ at the site. This will open up the site for new uses and secure the long term future of the gasholder and its place on the local skyline.

    Water removal

    Our specialist contractors, Erith, started by removing the water in the bottom of the gasholder. This was pumped out, treated on site and discharged into the local sewer under a consent from Anglian Water.   

     

    Image
    Pictured: Water removal process

     

    Before work started to remove the tank any oil and sludge inside the tank was removed. 

     

    Steel cutting

    Once the water, oil, sludge and other debris was removed, the tank was dismantled. This involved cutting the cast iron structure using a range of equipment. Some of  the metal has been stored on site for possible re-use in the future.

    This first part of the work began in September 2024 and was finished in May 2025 . 

    Image
    Pictured: Steel cutting

    Now the tank has been removed  detailed design work is underway to plan the refurbishment works. These works are likely to include: 

    • the removal of old paint and cleaning of the frame;
    • structural repairs to the cast iron frame as required; and
    • painting of the frame


    We will provide more information on this when the design stage is complete. We expect this stage of works to start in late 2025/early 2026 and be complete by the end of 2027.

    Image
    BA

     

    We're an approved Client Partner of the Considerate Constructors Scheme

    Which means that we will work with our appointed contractor, Erith, to: • demonstrate and promote the highest standards of considerate construction with our on-site activities; • undertake work in a way that is considerate of the general public, the workforce and the environment; and • act as ambassadors for the construction industry, promoting the Scheme and its aims, and will look to promote a positive image of construction at all times.
    More information

    More information on the site and community 

      Gasholders were used to store gas until it was needed by homes and factories. They were first used to store gas made from burning coal at local gasworks but were also used to store natural gas when this started to be used. 

      As gas was used the tanks fell and as they re-filled, usually at night, they rose again. Gasholders are no longer used as part of the national gas system as gas is now stored under pressure in a national network of pipes.

       

      The Great Yarmouth gasholder had a water filled cast iron tank, and within this were two containers which stored the gas called 'lifts'. 

      The top lift was sealed at one end (the crown) and sat over the water. As the top lift filled with gas it raised out of the tank until it connected to the second lift which then filled with gas. 

      The lifts were guided by wheels which ran on rails on the inside of the columns, stopping them blowing over in the wind. Water in the tank and between the lifts provided a seal preventing the gas from leaking. 

      Image
      Gas holder

      National Grid recognises that gasholders and gasworks are a part of our industrial heritage and how important it is to undertake historical recording at all gasholder sites.  

      At Great Yarmouth, Level Three Historic Building Recording is being undertaken given that the gasholder is Grade II Listed. When complete, this will be made available in the online record section of this website. 

      We have donated parts of the dismantled gasholder tank to the Fakenham Gas and Local History Museum,  retained some material on site for future use and we are working on a project with the Time and Tide Museum to create a permanent sculpture at the museum using metal from the gasholder tank.

      Site facts

      The Great Yarmouth Gas Company started making gas from coal in 1824 on a site on the banks of the River Yare. The Admiralty Road site dates back to the 1860s when they needed to build a new gasworks on a nearby site. As the demand for gas changed during the day, the gas was stored in gasholders until it was needed by local homes and businesses.  

      • The remaining gasholder at the site, known as Gasholder No. 172, is a column guided gasholder and dates from 1884

      • Including its finials, it is 29m high, has 14 cast iron columns and 52 lattice beams in the frame

      • It had a capacity of 385,000 cubic feet

      • The tank is made of rivetted cast iron plates with a diameter of 29.8m and contains two lifts which locked together to form one large space when it filled with gas

      The gasholder was designed by R.P Spice and built by Samuel Cutler & Sons, originally on a different part of the gasworks before being re-located to its current position in 1885. The gasholder was decommissioned in the early 2000s. 

      Professor Russell Thomas, a world renowned expert of the history of the gas industry,  has been commissioned to undertake a study on the history of the former gasworks site and the gasholder. His work will conclude with the publication of a booklet on the history of the site which will be freely available to download here when it is completed. 

      Updates

      Site neighbours will be kept up to date via letters, and we encourage the wider community to access updates via this website. Anyone with any questions can contact our community relations team via the contact section at the foot of this page.

      Community visits

      We welcomed local residents to site on 27 November 2024 to learn more about the gasholder and our work.

      Watch a short film about the visits 

      During these visits the team met George Tovell who worked on the gasworks when he was just 16 years old. In April 2025, we invited him back to share some of his memories. 

      George Tovell's interview

      T-Level Engineering students from East Coast College also visited site in February and March 2025.

      East Coast College students visit

      Two groups from the University of the Third Age (u3a) also had tours in March 2025.

      University of the Third A tour

      Organisations close to the work can also apply for funding through the Community Grant Programme, please get in touch for more information. 


      Online record

      As work progresses, this section will keep you up to date with an online record of dismantled and retained parts of the cast iron tank segments. It will also contain all documents released publicly about the project.
       

      Images

      © 2024 National Grid plc
       

      Videos

      The Great Yarmouth gasholder before works began

       

      Contact us

      If you have any questions about our work, you can contact a member of our community relations team on:

       

      0800 8199 071 

      9am - 5pm | Monday - Friday

      There is an answerphone service in case you need to reach us outside of these hours. 

       

      You can also get in touch by writing to us using our freepost address, you don't need to add an address or a stamp, simply put:

      Freepost IPB 

      Or email us at: [email protected]  

       

      Email us