Starting in April 2024, we will be carrying out essential upgrades to our existing overhead electricity line between Elstree Substation and Sundon Substation.

Latest Update (October 2024)

We're making good progress on work to refurbish and replace the wires and other equipment. We anticipate this work will continue along the 35km route until late-October 2024.

This planned work will not affect local electricity supplies to homes and businesses.

During this time, you may see teams, including the project’s main contractor Morgan Sindall, working along the overhead line where new wires will be installed and old ones removed.

The work will include vehicles and machinery to allow us to do the work safely, to move materials and equipment onto site and remove the old equipment, and to transport our workers to and from site.

We would like to thank everyone for their understanding while we carry out this essential work.

 

Our Elstree to Sundon refurbishment project will increase capacity and enable more clean energy projects in South England to be connected onto the UK electricity network.

The line runs south from Chalton, through Dunstable, past Hemel Hempstead and enters Elstree Substation to the east of Watford. 

Our programme to upgrade the line includes preparation activity, followed by the main works to replace the wires and other equipment along the 35km route. 

The Elstree to Sundon Refurbishment Project will commence its preparation activity in April 2024, with the main works taking place between June and October 2024.

This work forms part of the crucial programme of overhead line refurbishment across the UK. The components on overhead lines are designed to last up to 60 years. However, we programme refurbishments before that time so that the work isn’t so costly and extensive. 

Elstree to Sundon
Elstree to Sundon map route


Contact Us

If you would like any further information or to speak to a member of the community relations team about the works, please use the contact for on our website or via the contact details below. 

Email: [email protected]

Phone: 0800 915 3602


Frequently Asked Questions 

What preparation works will be taking place?

To ensure our work can happen as safely and efficiently as possible, we will be carrying out a number of activities in advance of the main works, which we describe as enabling works. 

This will include: 

  • Vegetation clearance and tree lopping
  • Widening road entrances at narrow access points
  • Installing scaffolding and trackways in fields
Who are you working with to deliver the project?

National Grid work with a number of contract partners to deliver their crucial works. The enabling and main works for this project are being led by Morgan Sindall, a construction and engineering company with a track record of delivering complex project for National Grid.

Why is it necessary to clear vegetation?

We need to clear some vegetation from around the base of some pylons and underneath overhead electricity lines so that our contractors can have safe access to work sites. 

National Grid is committed to ensuring as little impact on local wildlife and the environment as possible. We will work with an ecologist when we remove the vegetation to ensure the clearance is kept to a minimum.

What steps will you take to protect the environment?

Before beginning any project, we carry out an environmental assessment of any areas that may be affected by our work. This includes consulting with a wide range of local environmental groups and landowners to ensure that where possible, we avoid any potential impact on the environment or disruption to wildlife.

What is bell mouth widening and trackway installation?

To prepare for our main works, in some places we will need to widen access roads (also known as bell mouth widening) to ensure equipment can access the overhead electricity line safely and efficiently. Carrying out this work in advance of the main pylon refurbishment will ensure we keep disruption to a minimum. 

We may also need to install some temporary trackways in fields to access to the overhead electricity line. 

Why are you installing scaffolding?

We may need to install some scaffolding in advance of the main refurbishment works beginning in June. Installing scaffolding allows us to minimise disruption to roads and businesses underneath the overhead electricity line. 

Will there be any road closures?

We do not anticipate any road closures during the preparation stage of our project, which will take place from April to June 2024. 

When the main works begin in June 2024, we may at times need to temporarily close some roads or install some temporary traffic management measures near our works. We’ll be back in contact with more details before we begin the main works. 

Will the work affect access to my property?

Access will be maintained to all properties along the route during the works. If we anticipate that the work is likely to cause any disruption near your property, we will contact you in advance with more information.   

Will you need to close any footpaths?

Our overhead line crosses some Public Rights of Way (PRoW) and Permissive Rights of Way. So we will need temporary footpath closures and/or diversions for the safety of members of the public as we work overhead. Where we can, we will look to keep local communities informed in advance and we’ll do all we can to minimise any disruption as we do our work.

How will this project help the UK to reach net zero?

National Grid Electricity Transmission is to upgrade this 35km stretch of high voltage overhead electricity lines to increase capacity and enable more clean energy projects in South England to be connected onto the UK electricity network. 

The project is among the first in a series of circuit upgrades taking place across the country which aim to speed up connections to the electricity transmission network and support a secure, affordable and net zero energy system. 

This essential upgrade will ensure the long-term energy security for the South England on both the high-voltage electricity transmission network and the local distribution network supplied to homes and businesses.