Phase 2
Quarterly Auctions - October 2005 to December 2005
National Grid and Réseau de Transport d'Electricité are pleased to announce the results of the quarterly auctions held on 15 September 2005 for the period 23:00 30/09/05 to 23:00 31/12/05.
France to England
150 MW allocated to five separate market participants. The price and capacity for each successful bid is published below:
| Capacity |
Price per MW Per quarter - € |
|
50 |
37,810.00 |
|
25 |
37,800.00 |
|
25 |
37,800.00 |
|
25 |
37,775.00 |
|
25 |
37,770.00 |
|
150 |
|
England to France
150 MW allocated to four separate market participants. The price and capacity for each successful bid is published below:
| Capacity |
Price per MW Per quarter - €
|
|
50 |
750.00 |
|
50 |
731.00 |
|
25 |
730.00 |
|
25 |
726.00 |
|
150 |
|
[1] The identity of the bidders has not been published on the grounds of commercial confidentiality
Phase 1
Quarterly Auctions - October 2005 to December 2005
National Grid and Réseau de Transport d'Electricité are pleased to announce the results of the quarterly auctions held on 23 August 2005 for the period 23:00 30/09/05 to 23:00 31/12/05.
France to England
150 MW allocated to three separate market participants. The price and capacity for each successful bid is published below:
| Capacity |
Price per MW Per quarter - € |
|
50 |
35,875.00 |
|
25 |
35,855.00 |
|
75 |
35,850.00 |
|
150 |
|
England to France
150 MW allocated to three separate market participants. The price and capacity for each successful bid is published below:
| Capacity |
Price per MW Per quarter - € |
|
25 |
925.00 |
|
50 |
916.00 |
|
50 |
901.00 |
|
25 |
900.00 |
|
150 |
|
[1] The identity of the bidders has not been published on the grounds of commercial confidentiality