April 2005 to March 2006

Phase 2

Annual Auctions - April 2005 to March 2006
National Grid and Réseau de Transport d'Electricité are pleased to announce the results of the annual auctions held on 1 March 2005 for the period 23:00 31/03/05 to 23:00 31/03/06.

France to England
150 MW allocated to four separate market participants. The price and capacity for each successful bid is published below:

Capacity Price per MW
Per year - €
25
76,500.00
50
76,350.00
50
76,350.00
25
76,350.00
150

England to France
150 MW allocated to four separate market participants. The price and capacity for each successful bid is published below:

Capacity Price per MW
Per year - €
20
5,000.00
78
4,999.00
26
4,930.00
26
4,601.00
150
 

[1] The identity of the bidders has not been published on the grounds of commercial confidentiality

Phase 1

Annual Auctions - April 2005 to March 2006
National Grid and Réseau de Transport d'Electricité are pleased to announce the results of the annual auctions held on 15 February 2005 for the period 23:00 31/03/05 to 23:00 31/03/06.

France to England
150 MW allocated to four separate market participants. The price and capacity for each successful bid is published below:

Capacity Price per MW
Per year - €
30
68,255.00
25
68,101.00
70
68,100.00
25
68,100.00

150

 

England to France
150 MW allocated to four separate market participants. The price and capacity for each successful bid is published below:

Capacity Price per MW
Per year - €
21
3,775.01
25
3,701.00
100
3,700.00
4
3,700.00
150

[1] The identity of the bidders has not been published on the grounds of commercial confidentiality