Safe Control of Operations
Customer’s wishing to complete the final connection (in accordance with UIP/IGT Briefing Note 1) will be required to nominate competent individuals to act as Authorising Engineers (AE) and Competent Persons (CP) to manage and control the connection in line with National Grid’s SCO procedures. The customer must make an application to National Grid for their AE and CP registration and provide relevant evidence for assessment of competence.
If the evidence of competence is acceptable, the customer AE & CP must then undergo training and assessment on National Grid’s SCO procedures. Following successful completion of the training and assessment, National Grid will register the customer AE and CP on National Grid’s national permitry databases.
NOTE: Each connection will require a separate AE and CP i.e. the roles cannot be combined. The AE and CP role can be carried out within the UIP/IGT customer or their sub contract organisation, subject to National Grid’s SCO procedures.
Application packs for AE and CP registration should be requested from the National Grid Network Controller.
Safe Control of Operations
20 May 2008
1PQ form
Pre-Qualification for Registration of AE CP-Connection Operations
12 May 2008
MM1 & MM2 matrix
National Grid system for Competent Persons (CP) and Authorising Engineer (AE) SCO/STC matching matrix - to be completed by UIP/IGT applicants.
Many of the files available to download on this page are Acrobat PDF files. To access these you will need Acrobat Reader which is available from the Adobe web site.