National Transmission System (NTS) - Gas Connections

Welcome to the NTS Gas Connections Homepage. This page aims to provide information for developers of gas entry, exit and storage projects with some initial guidance on how to get a Transmission Connection to the NTS. In this case, Transmission Connection refers to:

A direct entry facility - a connection that will deliver gas into the NTS, or
A direct exit facility - a connection that will offtake gas directly from the NTS, or
A direct storage facility - a connection that will operate as a gas storage site on the NTS.

Please Note – Important: Any new NTS connection project must intend to flow in excess of 58,614,200 kWh (2,000,000 therms) per annum in order to be allowed to connect to the NTS. This equates to approximately 20,000 Domestic properties.

Industry led changes to the NTS Connections Processes:

Under the Uniform Network Code Modification Proposal 0373 “Governance of the NTS Connections processes”, the industry is reviewing the process of how projects obtain a new (or revised) NTS connection. We anticipate the implementation of a new NTS connections framework during 2012 to reflect the outcome of this review.

National Grid has commenced trialling a new Application process in readiness for an implementation of Mod0373.This web page is an interim solution and will be updated in parallel to events driven by the Mod0373. 

If you wish to familiarise yourself with the Mod0373, please use the following link to the Joint Office of Gas Transporters: www.gasgovernance.co.uk/0373

In the first instance, National Grid recommends that if you would like to discuss your requirements for a connection to the NTS then, after reviewing the basic NTS Connections Guide and the associated documents, please contact one of the following people for a pre application discussion. They will be happy to discuss with you in more detail the process of connecting to the NTS:

Basic Guide to obtaining an NTS connection

We have produced a basic guide to obtaining a connection to the NTS which can be downloaded here. This guide makes reference to a number of industry documents which can be found below

Generic Agreements
The Agreements which may be required to be entered into between National Grid Gas plc and [Users/Operators] shall be substantially in the form as those detailed below.

Generic Agreements

12 December 2011
Network Entry Agreement
12 December 2011
Storage Connection Agreement
12 December 2011
NExA - Minimum Offtake - Operator Only
12 December 2011
NExA - Minimum Offtake - Operator and Shipper
12 December 2011

12 December 2011

Generic Agreements - ARCA Consultation documents

31 January 2012
ARCA - Enduring Generic No Works
31 January 2012
Informal Consultation Response - BGT
31 January 2012
ARCA - Enduring Generic Works
31 January 2012
ARCA Consultation Report

Connection Related Documents

01 December 2011
Licence Condition 4b statement
01 December 2011
Transmission Planning Code
01 December 2011
Connection Charging Statement

Capacity Related Documents

01 December 2011
NTS Incremental Entry Capacity Release Methodology
01 December 2011
NTS Exit Capacity Release Methodology Statement

NTS Connection Application Form and Guide

09 March 2012
NTS Connection Application Form
This document is subject the the approval of mod 0373.
09 March 2012
Connection Application Guide
This document is subject the the approval of mod 0373.

Contact information

10 May 2012

View contacts
 

Many of the files available to download on this page are Acrobat PDF files. To access these you will need Acrobat Reader which is available from the Adobe web site.