This table is updated quarterly (from 1 January 2005) with information on accepted, rejected and not granted STTEC applications.
|
Date Received |
User |
Station Name |
GSP |
MW Requested |
STTEC Period |
Application Status* |
|
Q1 2005 - No commenced STTEC periods |
|
Q2 2005 |
|
28/02/2005 |
E.ON |
Killingholme |
Killingholme |
140 - 450 |
11/04/2005 - 08/05/2005 |
Accepted |
|
29/03/2005 |
E.ON |
Killingholme |
Killingholme |
140 - 450 |
09/05/2005 - 05/06/2005 |
Accepted |
|
21/04/2005 |
E.ON |
Killingholme |
Killingholme |
140 - 450 |
06/06/2005 - 03/07/2005 |
Accepted |
|
14/06/2005 |
E.ON |
Killingholme |
Killingholme |
420 - 450 |
06/06/2005 - 17/07/2005 |
Accepted |
|
Q3 2005 |
|
20/05/2005 |
|
|
|
450 - 900 |
04/07/2005 - 31/07/2005 |
Not Granted |
|
01/08/2005 |
E.ON |
Killingholme |
Killingholme |
440 - 450 |
15/08/2005 - 25/09/2005 |
Accepted |
|
13/09/2005 |
E.ON |
Killingholme |
Killingholme |
440 - 450 |
26/09/2005 - 06/11/2005 |
Accepted |
|
Q4 2005 |
|
12/10/2005 |
First Hydro |
Dinorwig |
Dinorwig |
100 - 177 |
31/10/2005 - 27/11/2005 |
Accepted |
|
20/10/2005 |
E.ON |
Killingholme |
Killingholme |
450 - 900 |
07/11/2005 - 18/12/2005 |
Accepted |
|
11/11/2005 |
First Hydro |
Dinorwig |
Dinorwig |
0 - 446 |
28/11/2005 - 25/12/2005 |
Accepted |
|
23/11/2005 |
Deeside Power |
Deeside |
Deeside |
10 |
12/12/2005 - 08/01/2006 |
Accepted |
|
07/12/2005 |
|
|
|
450 - 900 |
19/12/2005 - 29/01/2006 |
Rejected |
|
07/12/2005 |
E.ON |
Killingholme |
Killingholme |
450 - 900 |
19/12/2005 - 29/01/2006 |
Accepted |
|
08/12/2005 |
First Hydro |
Dinorwig |
Dinorwig |
0 - 446 |
26/12/2005 - 05/02/2006 |
Accepted |
|
Q1 2006 |
|
16/12/2005 |
E.ON |
Killingholme |
Killingholme |
450 - 900 |
02/01/2006 - 29/01/2006 |
Accepted |
|
23/12/2005 |
E.ON |
Killingholme |
Killingholme |
450 - 900 |
09/01/2006 - 12/02/2006 |
Accepted |
|
20/01/2006 |
First Hydro |
Dinorwig |
Dinorwig |
0 - 410 |
06/02/2006 - 16/03/2006 |
Accepted |
|
30/01/2006 |
E.ON |
Killingholme |
Killingholme |
450 - 900 |
13/02/2006 - 12/03/2006 |
Accepted |
|
Q2 2006 |
|
20/03/2006 |
|
|
|
430 - 450 |
03/04/2006 - 07/05/2006 |
Not Granted |
|
Q3 2006 - No commenced STTEC periods |
|
Q4 2006 - No commenced STTEC periods |
|
Q1 2007 |
|
08/02/2007 |
British Energy |
Torness |
Torness |
0 - 30 |
19/02/2007 - 31/03/2007 |
Accepted |
|
Q2 2007 - No commenced STTEC periods
Q3 2008
20/11/2008 Saltend Saltend Saltend 20 08/12/2008 - 18/01/2009 Accepted
Cogeneration
01/01/2009 Saltend Saltend Saltend 20 19/01/2009 - 01/03/2009 Not Granted
Cogeneration
|
* If the entry in this column is either 'Accepted' or 'Rejected', it relates to a decision made by the User. If the entry is 'Not Granted', it relates to a decision made by National Grid.